Battery test Ups systems Sdc1 Dronten

Dear Customer,

You are receiving this message as an advance notice of a planned inspection

Location = SDC1, Dronten, NL
Service Type = Ups systems

Start: 18.10.2017 20:00 CET
End: 18.10.2017 24:00 CET
Duration: 4 hours

Reason: Visual inspection and battery test of all the ups systems one by one. During the inspection all the values will be checked and verified.

Service impact: none
Service interruption : none

If you have any questions let us know at support@serverius.net

Maintenance of L2 Transport network between Nikhef, Amsterdam and SDC1, Dronten

Dear Customer,

You are receiving this message as an advance notice because we are going to do a maintenance on our Transport network.

Location = Nikhef, Amsterdam and SDC1, Dronten
Service Type = L2 transport

Start: 2017-07-20 22:00:00 CEST
End: 2017-07-20 23:00:00 CEST

Reason: At this year we faced with a lot of maintenances at fiber network in the Netherlands, During those maintenances our L2 transport service was affected and our clients had outages. Also, the total amount of traffic in our Transport network always increasing same as expectations of our clients to this service.
To avoid the outages in the future related with planned or emergency maintenances of out fiber suppliers and to increase the amount of ports and total capacity we have built the totally new Transport network. This network is based on the newest Huawei CloudEngine hardware and fully redundant fiber channels. It’s done like fully redundant and fully independent of main Serverius IP transit network.
New Transport network has available hardware at those locations:
– Nikhef, Amsterdam, NL
– GlobalSwitch, Amsterdam, NL
– SDC1, Dronten, NL
– SDC2, Meppel, NL
– TCN, Groningen, NL
– Interxion, Frankfurt, DE (coming soon)
Based on this new Transport network we can offer our clients different kind of services, such as:
– fully redundant L2 tunnels between any POPs on our network
– free of charge connection to our own Internet Exchange point and connections to our route servers for free exchange of IP traffic between all members of our exchange point.
– Low-latency IP transit service with BGP FlowSpec extensions.
– Protected IP transit service with AntiDDoS and Web Application Firewall protection.
– Connection to the AMS-IX exchange point
New Transport network is fully done and tested and ready for production usage.

Expected Outage: At this step of implementation, we should migrate all existing L2 vlans connections between Nikhef, Amsterdam and SDC1, Dronten to the new Transport network. Expected outage is up to 1 minute for reconnections.

Dark fiber maintenance of our supplier “Relined” PA-536002

Dear Customer,

You are receiving this message as an advance notice because our dark fiber suppliers “Relined” will do maintenance PA-536002.

Location = Nikhef, Amsterdam, NL
Service Type = Dark fiber

Start: 2017-08-27 00:00:00 CEST
End: 2017-08-27 06:00:00 CEST

Reason: Reconstruction
Due to reconstruction work carried out by the local authorities. Relined is obliged to relocate a section of her network. This action will result in a temporary interruption of the service.
This activity will impact the following dark fiber circuits: SDC1, Dronten<->NIKHEF, Amsterdam.

Expected Outage: Is expected downtime of DWDM channels from the DC1, Dronten to the NIKHEF(Amsterdam). None expected outage for IP transit service and L2 Transport service, other dark fibers will automatically take over the data traffic, but there is a small chance for high latency and short time packet loss in the time of rebuild routing tables.

We apologize in advance for any inconvenience this might cause.

Dark fiber maintenance of our supplier “Relined” PA-414001

Dear Customer,

You are receiving this message as an advance notice because our dark fiber suppliers “Relined” will do maintenance PA-414001.

Location = Nikhef, Amsterdam, NL
Service Type = Dark fiber

Start: 2017-08-06 00:00:00 CEST
End: 2017-08-06 06:00:00 CEST

Reason: Reconstruction
Due to reconstruction work carried out by the local authorities. Relined is obliged to relocate a section of her network. This action will result in a temporary interruption of the service.
This activity will impact the following dark fiber circuits: SDC1, Dronten<->NIKHEF, Amsterdam.

Expected Outage: Is expected downtime of DWDM channels from the DC1, Dronten to the NIKHEF(Amsterdam). None expected outage for IP transit service and L2 Transport service, other dark fibers will automatically take over the data traffic, but there is a small chance for high latency and short time packet loss in the time of rebuild routing tables.